돌관공사 시나리오 기반 공정관리 최적화 방안 / Process Optimization Method Based on Emergency Construction Work Scenario |
저자명 |
이시현(Lee, Si-Hyun) ; 이승학(Lee, Seung-hak) ; 우미선(Woo, Mi-Sun) ; 손재호(Son, Jae-Ho) |
발행사 |
한국건축시공학회 |
수록사항 |
한국건축시공학회 학술.기술논문발표회 논문집, Vol.15 No.1(통권 제28호) (2015-05) |
페이지 |
시작페이지(117) 총페이지(2) |
주제분류 |
시공(적산) |
주제어 |
돌관공사 ; 선형최적화 ; 시간-비용 상관관계 ; 공기단축//emergency construction work ; linear optimization ; TCTO ; duration reduction |
요약2 |
These days buildings have more possibilities to occur construction delay as many variables and risks are inherent in them due to the enlargement and complexity. When a project is delayed, it generates extra working expenses and this causes a dispute between the employer and the constructor. Most construction sites conduct emergency construction work to recover the delay of the project duration. When an emergency construction is carried out in the actual construction site, it’s necessary to utilize and distribute the proper working groups based on the procedure of successor and predecessor. Many constructions, however, have been going only with more number of work forces and working time. This study suggests a process management optimization plan with an application of emergency construction scenario by using linear programing. |
소장처 |
한국건축시공학회 |